March, 2009 - Construction started on 10,000 gallon chiller testing station – one of the largest in the Industry. To be completed and operational April 20th, 2009.
March, 2009 - (19) XTO air handling unit modifications – unit shells and fans were shipped and are reconfigured to meet design requirements. Includes pneumatic and DDC.
December, 2008 - Fisen Exceeds $22 Million Dollars in Modifications.
May, 2008 - (4) XTI 30,000+ cfm air handling units adding complete section of full cfm plate heat exchangers for large hospital.
September, 2007 - (13) Fully-custom all-aluminum 40-ton air VAV handling units with DDC, gas heat with stainless steel heat exchangers.
October, 2005 - 100th Custom project shipped.